Ignore Sunk Costs: Calculate Only What the Decision Still Changes
TL;DR
Money already spent is the same under every option. Set it aside, calculate forward value, compare against the next best use of the budget, then name the breaking point.
The client has already spent 8 million dollars building a new product. Finishing it will take 4 million more, and the launch is forecast to bring in 6 million of profit. Most candidates add it up: 8 plus 4 is 12 million of cost against 6 million of profit, so kill it. That answer sounds careful, and it is wrong. The 8 million is gone whatever the client decides. The strongest candidates take it off the table out loud, calculate only the money the decision still changes, and then compare against the best other use of the 4 million.
The rule in one line
Sunk costs out, opportunity costs in. Count only future cash that changes with the choice, and compare each option against the next best use of the same budget.
Why candidates get stuck
- They anchor on the total. A big number like 8 million already spent feels like it must matter. It does not, because no option gets it back.
- They compare against doing nothing. "Finishing makes 2 million" is only half the question. The 4 million could also fund something else.
- They stop without a breaking point. The interviewer wants to know what would have to be true for the other answer to win.
Want reps with feedback on this exact move? Practice calculate and so-what drills free at CaseCrunchAI.
The four step habit
1) Name the sunk cost and set it aside
"The 8 million is already spent. It is the same under every option, so I will leave it out of the comparison and focus on what is still ahead."
2) Calculate the forward value of finishing
"Finishing costs 4 million and earns 6 million of profit, so finishing is worth 6 minus 4, which is 2 million."
3) Bring in the opportunity cost
Ask: "Is there another use for that 4 million?" Say the interviewer tells you an expansion project would earn 7 million of profit on the same 4 million, and the budget only covers one. "The expansion is worth 7 minus 4, which is 3 million. That beats finishing by 1 million."
Sanity check it a second way, with the sunk cost left in. Finish: minus 8, minus 4, plus 6 is minus 6 million. Expansion: minus 8, minus 4, plus 7 is minus 5 million. Stop everything: minus 8 million. Expansion still wins by 1 million over finishing, and both beat stopping. The 8 million shifts every total by the same amount, which is why it never changes the ranking.
4) Find the breaking point and say the so-what
"Finishing wins only if its profit beats the expansion's 3 million of net value plus the 4 million to finish, so the launch needs more than 7 million of profit. At the forecast 6 million, I would put the 4 million into the expansion. If the team can show a path to more than 7 million, for example a higher price or a faster ramp, finishing comes back into play."
Mistakes to avoid
- Adding money already spent into the cost of an option.
- Comparing an option only against doing nothing instead of against the next best use of the budget.
- Giving a net number without the breaking point or a one sentence recommendation.
10-minute drill
Write five "should we keep going" scenarios, each with money already spent, cost to finish, forecast profit, and one alternative use of the same budget. Give yourself 45 seconds each, out loud: name the sunk cost and set it aside, calculate the forward value, compare it to the alternative, then state the profit the project would need to win. Record yourself and count every time you include the sunk cost in your math. Repeat until that count is zero.
Sunk costs out, opportunity costs in, then name the breaking point. That turns "we have already spent so much" into a recommendation the interviewer remembers.